Construction begins next week, the week of August 12th. This includes demolition, building of about 75 feet of walls with several doors, and hanging some slatwall. It should take a week.
The week of August 19th we'll be doing some electrical work: moving light switches, pulling power to the cash wrap and drink cooler, CAT5 for the network, telephone to the office (3 lines), 8 speakers with wiring for the game room and retail space, satellite radio, and installing track lighting.
The week of August 26th the property management company comes in and paints the place and lays carpet, preferably in that order.
The week of September 2nd, fixtures start arriving.
The week of September 9th, product starts arriving (it mostly goes on those fixtures). I estimate it will take approximately 40 hours to process all the new stuff, mostly toys. I'm giving it two weeks for things to settle.
The week of September 23rd we're moving!
The week of September 30th we'll be filming the new TV commercial, so things should be in place by then.