THIS WEEK (week of 8/26):
Monday: Exterior sign approved by landlord. Parts ordered by sign guy. Need city sign permit.
Monday-Tuesday: Painters are painting.
Tuesday Night: Electrical and wiring work starts.
Friday: Fixtures ship. Should arrive mid-week next week.
Friday-Saturday: Carpet installed.
NEXT WEEK (week of 9/2):
Friday-Monday: I'll be at Conquest San Francisco, spreading the word about the move and hopefully making a little money.
Tuesday: Telephone lines installed. ADT out for alarm system move estimate.
Wednesday-Friday: Fixtures begin arriving. Time to begin setting up!
WEEK 3(week of 9/9):
New game and toys begin shipping on the 10th along with a Games Workshop expansion.
Exterior sign will probably be installed this week.
Alarm system probably installed around this time.
WEEK 4 (week of 9/16):
Processing of new inventory should take approximately 45-50 hours
New air conditioning units installed
WEEK 5 (week of 9/23):
Sunday: Closed for move
Tuesday: Open for business. Ogre Kingdoms destroy opponents in evening battle of new campaign.